Before you start

SEMS plans with the customer's real contract data, so ask for the documents before the site visit and enter everything in one go.

Documents to ask for​

Ask for the latest electricity and network bill, the supply and buy-back contracts, the grid connection approvals for consumption, solar and battery, and the solar design with the single-line diagram.

Data to collect​

DataNeededWhere to find it
Site addressRequiredBill or contract
Connection power (kW)RequiredGrid connection approval, bill
Allowed export power (kW)RequiredConnection approval for the solar plant or battery
Agreed power for blocks 1–5 (kW)RequiredNetwork bill
Network user groupRecommendedNetwork bill
Network power charge per block (€/kW per month)RecommendedNetwork bill
Network energy charge per block (€/kWh)RecommendedNetwork bill
Supplier and productRequiredSupply contract, bill
Dynamic price: market and supplier fee (€/MWh and/or %)Required for dynamic contractsSupply contract
Fixed price: ET or VT/MT (€/kWh)Required for fixed contractsSupplier price list, bill
Buy-back price or formula, for example market price minus a feeRequiredBuy-back contract
May the battery charge from the grid, and may that energy be sold back?RequiredSupply and buy-back contracts, battery connection approval
Solar plant power (kWp), tilt and orientationRequiredSolar plant design
Position of the meter at the connection pointRequiredSingle-line diagram

Inverter and battery data such as capacity and power limits are read from the devices.

The answer on grid charging and resale sets the Electricity Plan switches that every strategy strictly follows.

On site​

SEMS needs a readable meter at the grid connection point. Plan a path to every device: RS485 for Modbus RTU, the CAN bus where a device uses it, and the local network for Modbus TCP, MQTT, REST and OCPP. The controller also needs internet for prices, forecasts and the monitoring portal, and the site's latitude and longitude.